ANDRECHUK – BASEMENT EXPANSION

This house is a 1950’s built bungalow with a large “footprint” but a small basement.  Most of the area under the house was crawl space.  The small portion that had a full basement had low ceiling height.  The client wanted to have a full basement under the entire house that he could develop and extend his living space into.

PROJECT GOALS

OUR APPROACH

  • Abarent Construction provided all of the Engineering and Plan Drawings for this project for which we were also responsible for obtaining the appropriate Building Permits.
  • We prepped the house then lifted the entire house off it’s existing foundation with the use of steel beams and cribbing.  The old foundation was demolished and the area completely excavated for new footings / foundation.
  • Following our Engineered Plan, we installed new footings and cribbed and poured new 9’ high foundation walls.  Alberta Building Code requirements were exceeded in all aspects of this footing / foundation design.
  • The new concrete foundation walls were damp-proofed and new weeping tile installed after which a passing green Sticker from a City of Edmonton Building Inspector was obtained.  The excavation was backfilled and all grading completed prior to the house being lowered onto it’s new home.
  • New Window locations were  “bucked” into the foundation during cribbing.
  • The new Engineered beam and column system was installed as well as installation of washed stone on the interior if the floor area.  We used stone as a base for the new concrete floor.  This is a “better building method” that provides a great compacted medium and a drainage course that can act as a backup to the exterior weeping tile system.
  • The floor area was properly prepared with vapor barrier, insulation, wire mesh and heating tubes for a hydronic in-floor heat system.

Another happy client with a basement area created by Abarent Construction.

WHAT OUR CUSTOMERS SAY

Abarent provided a 3-page, itemized list of the specific work to be done at each stage of the project, including descriptions of optional issues (including additional costs) that might arise during the work. The company president did the initial walk-through for their estimate and later went through it, line by line. He pointed out potential problems and things we had to prepare for during the work (extra cracks, concrete dust, effects on neighbors, etc.)… Repairing a foundation is a very traumatic event for any householder because all of your house investment is (literally!) in the air. If you have to do it, call Abarent. They are professional – we cannot recommend them highly enough.

John Baker

I would like to take this opportunity to thank you for a job well done. After this past weekend’s deluge, our basement was left completely dry.

Aileen & Wayne Dembicki

It is terrific to see that your company’s motto of “Quality without Compromise” is more than just words… The job was completed ahead of schedule and the workers ensured that when they left, the yard looked just like it did when they arrive. Well, actually it looked better…

Don and Eve Neil

We have had our fair share of unremarkable and even troublesome experiences with other contractors, so you guys were certainly a breath of fresh air. An honest contractor, bang on with the timeline, finished on time, within budget, your “nothing is too much trouble” attitude…and a job well done.

Michael Abbott